In under two months, I lost two machines. The first was my main production tool — my only tool, in truth. It degraded, then stopped, after a run of power cuts and voltage swings. I bought a replacement two weeks later, because without a machine I deliver nothing. The new one's motherboard burned out in turn, under the same conditions. The tally: two workstations dead, more than 700,000 CFA francs each. I am not writing this to complain, and I am not pointing at anyone. I am writing it because I had done my sums badly, and because I see plenty of freelancers and small outfits doing their sums exactly the way I did.
Two instabilities, two bills
For a long time I filed all of it in the same drawer: "the power goes out." That is an analysis error, and an expensive one. What kills a motherboard is electricity — the hard cut, the brutal surge when power comes back, the overvoltage. The component takes it, takes it again, then gives out one morning without warning. An internet outage breaks no circuit. It costs time: the photo upload that restarts from zero, the client video call that drops at the wrong moment, the deployment interrupted halfway. Two different problems. Two different costs. Two different answers. Confusing them means treating the wrong symptom and then being surprised that nothing improves.
The context, for its part, is documented. The World Bank identifies the cost and stability of electricity access as a major obstacle to digital development. In sub-Saharan Africa, roughly a third of rural schools have no stable electricity and more than two-thirds no reliable internet. In Togo, internet access remains expensive and uneven, and service interruptions are part of the daily life of businesses. On the other side, mobile penetration exceeds 70% of the population. That is real progress: the usage is there, massive, established. It is simply moving faster than the reliability of what carries it.
The visible cost hides the real cost
More than 1.4 million CFA francs of equipment: that is the line everyone sees, the one that hurts in the moment. It is not the heaviest. The heaviest is what I did not invoice while I was hunting for a machine, reinstalling a working environment, tracking down my files. It is the deliveries pushed back, the appointments postponed, the "I'll get back to you tomorrow" that becomes the day after. A client understands a breakdown. At the second one, he starts wondering whether the problem comes from me. That is the real bill: it is written on no receipt.
What I budget for now
A properly sized UPS and a surge protector, as a budget line. Not as an accessory to be bought "when things get better." On a 700,000 CFA franc workstation, decent electrical protection costs a fraction of the price of the machine, and it plays exactly the role of insurance. Properly sized means calculated for the real load of the workstation and the screen, not the first box on the shelf.
Automatic backup, somewhere other than the workstation. An external drive you plug in "every now and then" is not a backup, it is an intention. Automatic, scheduled, and verified by restoring a file at random once a month. A machine that dies must stay a hardware problem, never a data problem.
A way of working that holds up offline. I work locally, then I sync. My files, my notes, my code live on the machine and go up when the link comes back. The seamstress who takes her orders on WhatsApp does the same thing without putting it in those words: she writes in a notebook when the network drops, and copies it over afterwards.
A second internet connection, with another operator. One main subscription, a backup data plan on another network. The day one link goes down, the other holds. This is not a luxury, it is the reasoning of the neighbourhood mechanic who keeps a second 14 mm spanner in his toolbox.
Putting the breakdown in the price, and measuring it
Set money aside for replacement instead of absorbing it. A machine does not last forever, and under my working conditions it lasted less time than I had planned for. So I amortise it in my rates: a share of every invoice goes into an equipment envelope. The day a workstation gives out, I am not scrambling for 700,000 CFA francs, I have already put them aside.
Measure your hours of downtime. A notebook is enough: date, duration, what I could not do. After three months, you are no longer arguing about how it feels, you have a number of hours. That number turns a complaint into an investment decision, and it justifies the UPS, the second link, the backup drive, figures in hand.
None of this prevents a power cut. It only changes who pays for it, and how much. Two lost machines taught me that I had budgeted for my equipment without budgeting for the conditions it works in.
Resilience is either budgeted in advance or paid for at full price.